Decks clear for AI engineering at Thiruvananthapuram

Thiruvananthapuram: And finally work on the proposed engineering base of Air India at Chakka is all set to take off.
Salem-based Mukesh and Associates, which is the consultant of the project, has invited tenders for the construction of the hangars and allied works at an estimated cost of Rs 39 crore.
The expected completion period of the work is 10 months. The State Government had handed over 15 acres of land adjacent to the airport, near Chakka, to Air India free of cost in September 2006 and Prime Minister Manmohan Singh laid the foundation-stone for the project on November 1 the same year.
But Air India got actual possession of the land only a couple of weeks ago.
It was the delay in evicting the Trivandrum Rubber Works (TRW) from the land allotted to Air India, which caused the impasse.
The Government had distributed compensation to employees of TRW a couple of weeks ago, following which the firm, defunct over the last many years, moved out of the land.
A Government quarters and the labour camp of the Punj Lloyd located on the 15 acres allotted to Air India were evicted earlier. The last date for submitting the tender is January 23 and the tenders would be opened on the same day.
27/12/07 Newindpress
To Read the News in full at Source, Click the Headline