Chennai: The Rs 2,015-crore expansion project was supposed to be completed by now but there has been a further delay due to various limitations, said Mr E.P. Hareendranathan, Airport Director.
“But we expect the facility to be ready for trial runs by December. The airport will be functional by March next year.”
One of the issues was regarding the acquisition of Defence land for setting up a utility building, an a/c plant and substation. That has been ironed out and the land has been obtained, said Mr Hareendranathan.
The project involves extension of secondary runway (which is currently 2.07 km long) by 1.03 km.
There will be 14 additional parking bays. The international terminal building is also being expanded by 59,300 sq m.
Currently, the Chennai airport's capacity is 320-330 aircraft movements a day.
Passenger traffic for FY2011 was 12.05 million, while cargo traffic was three lakh tonnes (international) and 93,000 mt (domestic).
“We are unable to entertain more peak capacity requests but with the expansion, the movements will go up significantly,” said Mr Hareendranathan.
14/07/11 Swetha Kannan/TE Raja Simhan/Business Line
To Read the News in full at Source, Click the Headline
Wednesday, July 13, 2011
Home »
Airports Jul 2011
» New-look Chennai airport may be ready by March
New-look Chennai airport may be ready by March
Wednesday, July 13, 2011
Related Posts:
Govt’s plans to upgrade Indian airports hit an air pocketMumbai: India’s plans to develop and modernize airports in 35 cities other than the four metros has hit an air pocket even as domestic airlines contin… Read More
Failure to clear airport dues costs Kingfisher R100 croreNew Delhi: The Airports Authority of India (AAI) has encashed a bank guarantee of R100 crore of Kingfisher Airlines after the latter failed to clear a… Read More
Human traffickers nabbed at Delhi airportDelhi: Police at the Capital's Indira Gandhi International (IGI) Airport have arrested two persons on charges of human trafficking. The incident came … Read More
Boarding pass for next day's ticketMumbai: In a major security breach at the Mumbai airport, a Kingfisher Airlines passenger entered the airport, got a boarding pass and even cleared s… Read More
Planes to taxi slowly due to repair work at SaharMumbai: Starting from July 28, air passengers are likely to spend more time taxiing on the Mumbai airport, as some taxiways and parking stands will b… Read More
0 comments:
Post a Comment