Thursday, October 02, 2014

Navi Mumbai airport site preparation work to start from Jan 2015

Mumbai: City and Industrial Development Corporation (CIDCO) plans to start pre-development works including relocation of power transmission lines and reclamation of site of land for the Navi Mumbai airport from January.

The pre-development works will commence upon completion of land acquisition later this month.

Pre development and will take over a year for completion and are estimated to cost over Rs 2,000 crore. According to CIDCO's planning the first phase of Rs 14,500 crore Navi Mumbai airport will ready from December 2018.

"We have split the pre development works in parts. Our officials are fine tuning the details with Indian Institute of Technology,'' a senior CIDCO official. Bids for the works will be issued next week, sources said.
01/10/14 Aneesh Phadnis/Business Standard
To Read the News in full at Source, Click the Headline