Friday, February 16, 2018

Navi Mumbai airport to get Modi push, to handle 10 mn flyers every year

Mumbai: Prime Minister Narendra Modi will lay the foundation of the Rs 160-billion Navi Mumbai airport project on Sunday. First conceived nearly two decades ago, the airport project has missed several deadlines and has been mired in issues related to land acquisition and environment. With the existing Mumbai airport reaching saturation, the need for a second airport has become urgent. The prime ministerial push is expected to expedite the work.
Last month the GVK group and the City and Industrial Development Corporation of Maharashtra (Cidco) signed the concession agreement for the airport. The GVK group won the bid to construct the airport last February but the award letter was issued only in October. The group runs the existing Mumbai airport.
Here are all the top details of the airport project:
1) Master plan to be ready by April: According to the concession agreement, the first phase of the airport will have the capacity to handle a minimum of ten million passengers and 0.26 million tonnes of cargo each year. The airport master plan is being prepared and will be submitted to the government by April -- within 90 days of the signing of the concession agreement. Consulting firm Jacobs UK is working with the GVK group on the master plan. An architect will soon be selected through a competition to design the terminal building.
However, the first phase could be built to handle more than ten million passengers per year and the same is being evaluated by GVK group. The evaluation will take into account factors such as traffic forecast, capacity at the existing airport in Mumbai, connectivity, and project financing, among other things.
2) Twenty per cent pre-development work complete: The core airport land covers 1,160 hectares and much of it comprises hillock, marshland, and river.

Pre-development works, which include flattening a hillock, reclaiming marshland, diverting a river, and shifting of power transmission lines, began last June. The work was held up many times by project-affected villagers but Cidco officials claim that the work has been completed on around 20 per cent of the 1,160 hectares. The hillock is being excavated and rock is being used to fill land to increase the land level to 5.5 metres above sea level. The work of shifting power transmission lines is yet to begin. The work requires clearance of the high court as it involves the construction of two stilt bridges over mangroves and creek.
17/02/18 Aneesh Phadnis/Business Standard

To Read the News in full at Source, Click the Headline

0 comments:

Post a Comment