New parallel taxi track at Vizag airport ready for operation

Visakhapatnam: The mandatory procedures for commissioning of the new parallel taxi track- N5 - at Visakhapatnam International Airport have been completed and it is ready for operation. Though it has already been notified in the Aeronautical Information Publication(AIP), a formal commissioning is awaited.

The Airports Authority of India(AAI) had spent ₹23 crore on construction of N 5 and six additional parking bays at the airport. A total of 12 big aircraft can be parked at the airport now. In addition to this, four smaller aircraft can also be parked at the old terminal building. These facilitates parking for airlines operating late in the night and for early morning departures from the city.

Once N 5 is commissioned it will help in increasing the number of flight movements by two an hour. Though the construction of N 5 taxi track was completed sometime in November 2019, it could not be commissioned immediately as there were several procedural issues to be followed. These included safety inspections by various agencies and sending information on the new taxi track to airports across the globe.

The subsequent lockdown and restrictions on movement of flights due to COVID-19 resulted in further delays. “We are planning for the inauguration of N 5 by August 16. We have invited Visakhapatnam MP and the Flag Officer Commanding-in-Chief of the Eastern Naval Command (ENC) for the launch,” said Airport Director K. Srinivasa Rao.

02/08/21 B. Madhu Gopal/The Hindu