Thursday, September 07, 2023

Upcoming int’l airport at Halwara 90% complete, to be ready by September 30

Ludhiana: The upcoming integrated civil enclave and cargo terminal at the Air Force Station in Halwara, which is one of the oldest frontline airbases of the Indian Air Force (IAF), close to Ludhiana, has been completed 90 per cent and will be ready by September 30, the government has confirmed.

After missing the sixth deadline of completion, which was fixed as August 30, allied works of the Rs 47-crore civil aviation project are now targeted to be completed by October 31, officials have said.

Even as the big ticket project has missed several deadlines, the construction of the interim terminal building has touched 85 per cent completion while the sub-station and toilet block was 90 per cent complete till date.

The development assumes significance as the Union Civil Aviation Ministry had recently assured to launch flights from here once the airport gets operational.

Rajya Sabha MP from Ludhiana Sanjeev Arora told The Tribune on Monday that the ongoing construction work had already reached the advanced stage of completion with the overall progress of the mega project touching 90-per cent mark.

Arora, who reviewed the progress of the project, said the recent incessant rains had delayed the ongoing work after the construction site was waterlogged. “Now, the construction firm has sought one more month to meet the deadline beyond the earlier fixed target date of August 30,” he revealed.

He said the state government had so far released a sum of Rs 30 crore to complete the ongoing balance work of the upcoming international airport and the demand of balance funds had already been forwarded to the Greater Ludhiana Area Development Authority (GLADA) and the Civil Aviation Department, which had been mandated to jointly bear the financial burden.

Divulging the component-wise status, the Rajya Sabha MP said the construction of the interim terminal building had touched 85-per cent mark, sub-station 90 per cent, and toilet block had been completed 90 per cent. All these three components of the new airport were now scheduled to be completed by September 30.

07/09/2023 Nithin Jain/Tribune