Chennai: Airport authorities have begun testing equipment at the new-look Chennai airport.
With the Tamil Nadu Electricity Board providing the power supply at the project area, testing began late last week, said Mr E.P. Hareendranathan, Airport Director, Chennai.
Electro mechanical equipment such as conveyor systems, lifts, air-conditioning and security systems are being tested.
The tests have to go on for at least a month, before the airport is ready for flight takeoff. The power requirement at the expanded airport is around 110 KVA – more than three times the current need.
31/03/12 Business Line