New terminals at Chennai airport cost Rs 200 cr more: AAI


Chennai: The Airports Authority of India (AAI) had to shell out an additional Rs 200 crore on the newly constructed international and domestic terminals at Chennai due to delay in completion of the project.
When the project was conceived in November 2008, the project cost was Rs 1,808 crore. This has increased to Rs 2015 crore, said V.P. Agrawal, Chairman, AAI.
The airport will be inaugurated on Thursday by Vice-President Hamid Ansari in the presence of Tamil Nadu Governor S. Rosaiah and Chief Minister J. Jayalalithaa.
While functionally the new terminals are ready, it will take another month or so to start operations. There are a few issues to be sorted out with the airlines, he told newspersons.
30/01/13 Business Line