Civil aviation minister reviews progress of Hollongi airport project

Itanagar:  Civil Aviation Minister Nakap Nalo on Thursday took a review meeting of the progress of Hollongi green field airport here at his office.
Regional Executive Director (NER) of the Airports Authority of India, Sanjeev Jindal; state Director of Civil Aviation, Tamiyo Tatak; POWERGRID, Nirjuli Senior General Manager C Borkotoky and the chief engineers of the departments of Public Works, Power, PHE&WS, UD & Housing were present in the meeting.
Presenting the status of progress, the AAI regional executive director informed that they are going to “start the first phase of work for the runway (Length 2300 m for operation of A320), pavement works, watch tower, perimeter road etc by the first week of February and the tenders for the second phase of works for terminal building and other constructions is likely to be finalized in April, 2020.”
The state work agencies informed that shifting of 11 KV LT power line passing through the project site will be completed by March, 2020 and works for bulk water supply and power supply, boundary wall, 4-lane approach road and other works will also commence by February.
24/01/20 Arunachal Times